|
Network analysis by CPM and PERT method was
proposed in the fifties. After fifty years
of use one still finds that majority of projects
are prone to delay. Dr. Goldratt
proposed the concept of critical chain first
time in 1997 to improve upon the idea of the
network analysis.
Goldratt defines the Critical Chain as the
longest chain of tasks that consider both task
dependencies and resource dependencies. This is
different from the definition of the Critical
Path, which is defined as the longest chain of
tasks based upon task dependencies. This is a
subtle, but important difference. Critical Chain
recognizes that a delay in resource availability
can delay a schedule just as a delay in
dependent tasks.
In Critical Chain Planning mode, one develops a
plan backwards in time from a target end date
for the project. This focus on completion date
is natural. In traditional Critical Path
scheduling, the tasks are scheduled
as-soon-as-possible (ASAP) from the project
start date. This scheduling places work as close
as possible to the front of your schedule. In
Critical Chain planning, the tasks are scheduled
as-late-as- possible (ALAP) based upon the
target end date. This as-late-as-possible
scheduling places work as close as possible to
the end of your schedule.
Critical Chain task estimating requires a change
in individual and organizational behavior
to be effective. One wants to remove the hidden
safety in the task durations Now, because this
safety is hidden, one has to establish an
organizational culture that removes the fear of
exposing this safety and removing it from task
estimates.
After taking out the safety from the tasks one
forms a pool of this safety and place it as
shock absorber buffers at key points in the
project. These buffers automatically
contract when they are pushed by overrunning
tasks and absorb the overruns without affecting
the target end
date.
There are a few software packages available to
generate and manage a critical chain network.
Some of the examples are provided.
Prochain: Prochain was the first
and one of the leading product in critical chain
scheduling. ProChain provides advanced
capabilities for creating integrated project
plans, resolving conflicts, focusing on key
tasks, and creating and maintaining reliable
critical chain schedules. Prochain is
integrated to Microsoft Project.
PS8:
PS8 from Sciforma company is a standard product
in critical chain scheduling. PS 8
provides a robust implementation of critical
chain, including planning backwards from a
target end date, removal of resource contention,
critical chain identification, automatic buffer
calculation and insertion, and automatic buffer
absorption during project execution. These
features are seamlessly integrated into PS8.
Multi-project critical chain is supported,
including synchronizing of project portfolio
based upon project priority and loading of key
resources. A buffer incursion curve is
from PS8 is presented.

CC
Pulse: cc-Pulse assists the
project team in making a feasible schedule,
immunized from the effects of variation with
project buffers (Project Tolerance) and feeding
buffers (Component Tolerance). The end of the
project buffer or project tolerance denotes a
protected commitment date for the project’s
customers. And once project duration is
established with cc-Pulse and the leadership
determines the project sequence, cc-MPulse
(multiple project management version) staggers
the projects on the timeline; reducing work in
process to levels the system of resources can
process at full speed.
The Looking Glass module of CCPM is a
graphical executive information system; a
dashboard, that brings Statistical Process
Control (SPC) and buffer management to the world
of project management. The Looking Glass
presents a graphical multi-project view that
allows executives to assess at a glance the
state of their multi-project system. A
view of Looking glass is presented herein.


|